Project Schedule Management Inputs, Tools and Techniques, and Outputs
by Project Management Process Group
1. Plan Schedule Management
Inputs | Tools and techniques | Outputs |
---|
- Project charter
- Project management plan
- Scope management plan
- Development approach
- Enterprise environmental factors
- Organizational process assets
| - Expert judgment
- Data analysis
- Meetings
| - Schedule management plan
|
Source: PMBOK® Guide, 6th ed., Chapter 6, section 6.1, p. 179.
2. Define Activities
Inputs | Tools and techniques | Outputs |
---|
- Project management plan
- Schedule management plan
- Scope baseline
- Enterprise environmental factors
- Organizational process assets
| - Expert judgment
- Decomposition
- Rolling wave planning
- Meetings
| - Activity list
- Activity attributes
- Milestone list
- Change requests
- Project management plan updates
- Schedule baseline
- Cost baseline
|
Source: PMBOK® Guide, 6th ed., Chapter 6, section 6.2, p. 183.
3. Sequence Activities
Inputs | Tools and techniques | Outputs |
---|
- Project management plan
- Schedule management plan
- Scope baseline
- Project documents
- Activity attributes
- Activity list
- Assumption log
- Milestone list
- Enterprise environmental factors
- Organizational process assets
| - Precedence diagramming method
- Dependency determination and integration
- Leads and lags
- Project management information system
| - Project schedule network diagrams
- Project documents updates
- Activity attributes
- Activity list
- Assumption log
- Milestone list
|
Source: PMBOK® Guide, 6th ed., Chapter 6, section 6.3, p. 187.
4. Estimate Activity Durations
Inputs | Tools and techniques | Outputs |
---|
- Project management plan
- Schedule management plan
- Scope baseline
- Project documents
- Activity attributes
- Activity list
- Assumption log
- Lessons learned register
- Milestone list
- Project team assignments
- Resource breakdown structure
- Resource calendars
- Resource requirements
- Risk register
- Enterprise environmental factors
- Organizational process assets
| - Expert judgment
- Analogous estimating
- Parametric estimating
- Three-point estimating
- Bottom-up estimating
- Data analysis
- Alternatives analysis
- Reserve analysis
- Decision making
- Meetings
| - Duration estimates
- Basis of estimates
- Project documents updates
- Activity attributes
- Assumption log
- Lessons learned register
|
Source: PMBOK® Guide, 6th ed., Chapter 6, section 6.4, p. 195.
5. Develop Schedule
Inputs | Tools and techniques | Outputs |
---|
- Project management plan
- Schedule management plan
- Scope baseline
- Project documents
- Activity attributes
- Activity list
- Assumption log
- Basis of estimates
- Duration estimates
- Lessons learned register
- Milestone list
- Project schedule network diagrams
- Project team assignments
- Resource calendars
- Resource requirements
- Risk register
- Agreements
- Enterprise environmental factors
- Organizational process assets
| - Schedule network analysis
- Critical path method
- Resource optimization
- Data analysis
- What-if scenario analysis
- Simulation
- Leads and lags
- Schedule compression
- Project management information system
- Agile release planning
| - Schedule baseline
- Project schedule
- Schedule data
- Project calendars
- Change requests
- Project management plan updates
- Schedule management plan
- Cost baseline
- Project documents updates
- Activity attributes
- Assumption log
- Duration estimates
- Lessons learned register
- Resource requirements
- Risk register
|
Source: PMBOK® Guide, 6th ed., Chapter 6, section 6.5, p. 205.
6. Control Schedule
Inputs | Tools and techniques | Outputs |
---|
- Project management plan
- Schedule management plan
- Schedule baseline
- Scope baseline
- Performance measurement baseline
- Project documents
- Lessons learned register
- Project calendars
- Project schedule
- Resource calendars
- Schedule data
- Work performance data
- Organizational process assets
| - Data analysis
- Earned value analysis
- Iteration burndown chart
- Performance reviews
- Trend analysis
- Variance analysis
- What-if scenario analysis
- Critical path method
- Project management information system
- Resource optimization
- Leads and lags
- Schedule compression
| - Work performance information
- Schedule forecasts
- Change requests
- Project management plan updates
- Schedule management plan
- Schedule baseline
- Cost baseline
- Performance measurement baseline
- Project documents updates
- Assumption log
- Basis of estimates
- Lessons learned register
- Project schedule
- Resource calendars
- Risk register
- Schedule data
|
Source: PMBOK® Guide, 6th ed., Chapter 6, section 6.6, p. 222.