PMP Certification: Project Scope Management Inputs, Tools and Techniques, and Outputs (based on PMBOK® Guide, 6th Edition)


Here your free guide to PROJECT SCOPE MANAGEMENT inputs, tools and techniques, and outputs. Pass your PMP Certification Exam. FAST, EASY!

Image titled pmp certification inputs tools and techniques and outputs pmbok guide 6th edition

Project Scope Management Inputs, Tools and Techniques, and Outputs

by Project Management Process Group

1. Plan Scope Management


InputsTools and techniquesOutputs
  1. Project charter
  2. Project management plan
    • Quality management plan
    • Project life cycle description
    • Development approach
  3. Enterprise environmental factors
  4. Organizational process assets
  1. Expert judgment
  2. Data analysis
    • Alternatives analysis
  3. Meetings
  1. Scope management plan
  2. Requirements management
    plan

Source: PMBOK® Guide, 6th ed., Chapter 5, section 5.1, p. 134.

2. Collect Requirements


InputsTools and techniquesOutputs
  1. Project charter
  2. Project management plan
    • Scope management plan
    • Requirements management plan
    • Stakeholder engagement plan
  3. Project documents
    • Assumption log
    • Lessons learned register
    •  Stakeholder register
  4. Business documents
    • Business case
  5. Agreements
  6. Enterprise environmental factors
  7. Organizational process assets
  1. Expert judgment
  2. Data gathering
    • Brainstorming
    • Interviews
    • Focus groups
    • Questionnaires and surveys
    • Benchmarking
  3. Data analysis
    • Document analysis
  4. Decision making
    • Voting
    • Multicriteria decision analysis
  5. Data representation
    • Affinity diagrams
    • Mind mapping
  6. Interpersonal and team skills
    • Nominal group technique
    • Observation/conversation
    • Facilitation
  7. Context diagram
  8. Prototypes
  1. Requirements documentation
  2. Requirements traceability matrix

Source: PMBOK® Guide, 6th ed., Chapter 5, section 5.2, p. 138.

3. Define Scope


InputsTools and techniquesOutputs
  1. Project charter
  2. Project management plan
    • Scope management plan
  3. Project documents
    • Assumption log
    • Requirements documentation
    • Risk register
  4. Enterprise environmental factors
  5. Organizational process assets
  1. Expert judgment
  2. Data analysis
    • Alternatives analysis
  3. Decision making
    • Multicriteria decision analysis
  4. Interpersonal and team skills
    • Facilitation
  5. Product analysis
  1. Project scope statement
  2. Project documents updates
    • Assumption log
    • Requirements documentation
    • Requirements traceability matrix
    • Stakeholder register

Source: PMBOK® Guide, 6th ed., Chapter 5, section 5.3, p. 150.

4. Create WBS


InputsTools and techniquesOutputs
  1. Project management plan
    • Scope management plan
  2. Project documents
    • Project scope statement
    • Requirements documentation
  3. Enterprise environmental factors
  4. Organizational process assets
  1. Expert judgment
  2. Decomposition
  1. Scope baseline
  2. Project documents updates
    • Assumption log
    • Requirements documentation

Source: PMBOK® Guide, 6th ed., Chapter 5, section 5.4, p. 156.

5. Validate Scope


InputsTools and techniquesOutputs
  1. Project management plan
    • Scope management plan
    • Requirements management plan
    • Scope baseline
  2. Project documents
    • Lessons learned register
    • Quality reports
    • Requirements documentation
    • Requirements traceability matrix
  3. Verified deliverables
  4. Work performance data
  1. Inspection
  2. Decision making
    • Voting
  1. Accepted deliverables
  2. Work performance information
  3. Change requests
  4. Project document updates
    • Lessons learned register
    • Requirements documentation
    • Requirements traceability matrix

Source: PMBOK® Guide, 6th ed., Chapter 5, section 5.5, p. 163.

6. Control Scope


InputsTools and techniquesOutputs
  1. Project management plan
    • Scope management plan
    • Requirements management plan
    • Change management plan
    • Configuration management plan
    • Scope baseline
    • Performance measurement baseline
  2. Project documents
    • Lessons learned register
    • Requirements documentation
    • Requirements traceability matrix
    • Work performance data
  3. Organizational process assets
  1. Data analysis
    • Variance analysis
    • Trend analysis
  1. Work performance information
  2. Change requests
  3. Project management plan updates
    • Scope management plan
    • Scope baseline
    • Schedule baseline
    • Cost baseline
    • Performance measurement baseline
  4. Project documents updates
    • Lessons learned register
    • Requirements documentation
    • Requirements traceability matrix

Source: PMBOK® Guide, 6th ed., Chapter 5, section 5.6, p. 167.

Click here for a detailed analysis of each project management process group and knowledge area.

SOURCES: Project Management Institute (2017). A Guide to the Project Management Body of Knowledge (PMBOK® Guide). 6th ed. Newtown Square: Project Management Institute.

pmbok 6th edition, project management certification, pmp certification course online, project management certification pmp, best project management certification, pmp certification preparation, project management professional certification, project management certification requirements, pmp course, project management cert, pmp certification course, pmp certification online, pmp classes online, pmp training online, pmp online training, pmp 2018.