Project Schedule Management (by Process Groups) — PMBOK® Guide, 6th Edition Update
Click here for a detailed analysis of each project management process group and knowledge area.
Control Schedule 101
What Does Control Schedule Involve and When Do You Perform It in a Project Life Cycle?
- WHAT Control Schedule Is. Control Schedule implies keeping all of the documents elaborated during the Develop Schedule process up to date and turning work performance data into work performance information.
- WHY Control Schedule Is Important. In the Control Schedule process, a project manager determines the current schedule status of the project and responds appropriately to any observed and measured variance.
- WHEN Control Schedule Is Executed. A project manager uses the Control Schedule process until all project activities are completed, that is until the end of the project life.
- HOW Control Schedule Operates.
Inputs | Tools and techniques | Outputs |
---|---|---|
|
|
|
Source: PMBOK® Guide, 6th ed., Chapter 6, section 6.6, p. 222.
Control Schedule Key Terms
What Are the Key Terms to Fully Understand the Process of Controlling Schedule?
- Schedule Forecasts. The updated projections of future performance based on actual performance.
- Work Performance Data. The raw data about how the project is progressing related to the schedule; e.g., implementation of change requests, preventive actions taken, percent of work actually completed, and so on.
- Work Performance Information. The processed work performance data, changed from raw data into reports that can be used to make project decisions; e.g., status of the deliverables, lessons learned, forecasted completion dates, and so on.
Control Schedule Tips
What Are the Best Tips to Answer Correctly the PMP Cerification Exam Questions on Control Schedule Process?
- Odds of Fast-Track and Crashing. Crashing is expensive and fast-tracking is risky. They might work sometimes but they always add both risk and cost to the project.
- Schedule Change Vs. Schedule Revision Vs. Schedule Update.
- A schedule change must be approved via the Perform Integrated Change Control process.
- A schedule revision, such as a change to the start and finish dates within an activity’s float, does not impact the baseline schedule.
- A schedule update enters status into a project schedule.
Click here for a detailed analysis of each project management process group and knowledge area.
SOURCES: Project Management Institute (2017). A Guide to the Project Management Body of Knowledge (PMBOK® Guide). 6th ed. Newtown Square: Project Management Institute. Project Management Institute (2016)
pmbok 6th edition, 35 hours of project management education, best project management certification, get pmp certified, how to get pmp certification, how to get pmp certification online, it project management certification, pmi pmp certification, pmp boot camp, pmp bootcamp, pmp certification, pmp certification atlanta, pmp certification boot camp, pmp certification classes, pmp certification cost, pmp 2018.